Mozambique - Power Efficiency and Reliability Improvement Project (الإنجليزية)

Ratings for Mozambique's Power Efficiency and Reliability Improvement Project were as follows: overall outcome, bank performance was satisfactory, and monitoring and evaluation quality was modest. Some lessons learned included the following: a government’s clear vision and priorities for a sector’s development can attract the long-term engagement of the World Bank Group and DPs through support for sector strategies and properly sequenced operations...
انظر المزيد

تفاصيل

  • 2025/3/28

  • تقرير إنجاز تنفيذ ونتائج المشروع

  • ICR00354

  • 1

  • موزامبيق,

  • Eastern and Southern Africa,

  • 2025/3/29

  • Disclosed

  • Mozambique - Power Efficiency and Reliability Improvement Project