Ratings for the Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Integration Program for Eastern and Southern Africa were as follows: outcomes were satisfactory, the Bank performance was satisfactory, and the monitoring and evaluation quality was substantial. Some lessons learned included: the implementation arrangements might have set up a two-country special purpose vehicle (SPV). Such a SPV arrangement might...
انظر المزيد
تفاصيل
-
2024/7/29
-
تقرير إنجاز تنفيذ ونتائج المشروع
-
ICR0049
-
1
-
2024/7/30
-
Disclosed
-
Eastern and Southern Africa - Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Integration Program