Ratings for the Thermal Power Project for Ghana were as follows: outcomes were moderately unsatisfactory; the risk to development outcome was substantial; Bank performance was moderately unsatisfactory; and the Borrower performance was moderately unsatisfactory. Some lessons learned included: when technologies in the energy sector are new to a country, the length of the Operations and Maintenance (0&M) contract should extend at least up until the...
انظر المزيد
تفاصيل
-
2007/9/07
-
تقرير إنجاز تنفيذ ونتائج المشروع
-
ICR320
-
1
-
1
-
2010/7/01
-
Disclosed
-
Ghana - Thermal Power Project
-
financial and private sector development
تنزيل الملفات
تقرير كامل
نسخة رسمية من الوثيقة (قد تضم توقيعات، الخ)
-
Total Downloads** : 624