Ratings for the Rural Roads Project for South Sudan were as follows: outcomes were moderately satisfactory, the risk to development outcome was high, the Bank performance was satisfactory, and the Borrower performance was also satisfactory. Some lessons learned included: Denominating works contracts in USD or in an equivalent stable currency, as well as including price variation clauses in the contracts, may mitigate risks associated with the devaluation...