Skip to Main Navigation

Cameroon - Second Semry Rice Project (الإنجليزية)

This is a performance audit of the Second SEMRY Rice Project. The First SEMRY Rice Project was implemented with only minor delays and a small cost overrun. The project got off to a quick start and generally proceeded on schedule during the first three years. However, two problems arose: the reservoir embankment dike experienced serious erosion and seepage problems, and an imbalance developed between land available for cultivation and actual land use...
انظر المزيد

الوثيقة أيضا متوفرة بـ الفرنسية

تفاصيل


This document is being processed or is not available.