Skip to Main Navigation

Albania - Critical Imports Project (الإنجليزية)

Ratings for the First Critical Imports Project for Albania were as follows: outcome was satisfactory, sustainability was uncertain, institutional development was modest, Borrower performance was highly satisfactory, and Bank performance was highly satisfactory. Some lessons learned included: for all types of emergency operations designed to address key social needs and or production bottlenecks, projects require a maximum degree of funding flexibility...
انظر المزيد

تفاصيل

تنزيل الملفات

تقرير كامل

نسخة رسمية من الوثيقة (قد تضم توقيعات، الخ)


This document is being processed or is not available.