Argentina - Fourth Buenos Aires Power Project (الإنجليزية)

This is the Project Completion Report( PCR) of Fourth Buenos Aires Power Project (SEGBA IV) for Argentina which was approved in September1 976. The objective of the project was to help finance expansion of transmission and distribution lines, substations, and studies of Servicios Electricos del Gran Buenos Aires (SEGBA). SEGBA IV was completed about four and one-half years late due to reduced investment expenditures required to take account of counterpart...