Ratings of Zarafshon Irrigation Rehabilitation and Management Improvement Project for Tajikistan were as follows: outcome was satisfactory, Bank performance was satisfactory, and monitoring and evaluation quality was substantial. Some of the lessons learned include: (i) Long-term cooperation between the government and the World Bank as well as strong ownership and commitment by and capacity of the Project Management Unit (PMU) played a key role in...