The Zanzibar Urban Services Project for Tanzania had a satisfactory outcome with moderate risk to development outcome and satisfactory performance by both the Bank and the borrower. The lessons learned were: (1) A high-level steering committee to engage key line ministries and to ensure multisectoral collaboration is key to ensure the effectiveness of the institutional arrangements. (2) Adopting an integrated urban development approach for infrastructure...