Ratings for the Road Sector Development Project for Burundi were as follows: outcomes were moderately satisfactory, the risk to development outcome was high, the Bank performance was moderately unsatisfactory, and the Borrower performance was also moderately unsatisfactory. Some lessons learned included: in post conflict situations, the peace-building process is the key objective, while the governments’ capacity to rebuild the nation is usually low...
انظر المزيد
تفاصيل
-
2016/2/01
-
تقرير إنجاز تنفيذ ونتائج المشروع
-
ICR3367
-
1
-
1
-
2016/2/03
-
Disclosed
-
Burundi - Road Sector Development Project
-