Overall, the project outcome is satisfactory, sustainability likely, and the institutional development impact high. Key lessons learned follow. Given the nature of an emergency operation, as in this case, where a speedy implementation is of the essence, project design should be simple, mainly concentrating on physical reconstruction. Therefore, policy formulation, particularly when it involves long-term issues such as institutional development, needs...
انظر المزيد
تفاصيل
-
2002/6/21
-
تقرير إنجاز تنفيذ ونتائج المشروع
-
24167
-
1
-
1
-
2010/6/18
-
Disclosed
-
Croatia - Emergency Transport and Mine Clearing Project
-
social and economic recovery