Ratings for the Jiangxi Wuxikou Integrated Flood Management Project for China were as follows: outcome was highly satisfactory, Bank performance was satisfactory, and monitoring and evaluation (M and E) quality was high. Some lessons learned included: flood management needs to be risk-based and to integrate both structural and non-structural measures. Flood-protection dams are high-risk, high-reward investments that should be carried out with sufficient...
انظر المزيد
تفاصيل
-
2021/1/26
-
تقرير إنجاز تنفيذ ونتائج المشروع
-
ICR5373
-
1
-
1
-
2021/2/04
-
Disclosed
-
China - Jiangxi Wuxikou Integrated Flood Management Project
-
flood