Executive summary for the Aynak copper mine (الإنجليزية)

The current project involves a two-phase development of the Aynak copper mine including a processing plant with a capacity of 30 ktpd of ore in phase one and 60 ktpd in phase two. The proposed alternative involves: 1) building a processing plant with a capacity of only 10 ktpd of ore, or a third of size envisaged in phase one, 2) relying on a mining contractor, and 3) renting diesel generators to supply power. This alternative project would reduce...
انظر المزيد

الوثيقة أيضا متوفرة بـ داري, البشتو

تفاصيل

  • 2013/4/01

  • مذكرة موجزة

  • 79738

  • 1

  • 1

  • أفغانستان,

  • جنوب آسيا,

  • 2013/7/24

  • Disclosed

  • Executive summary for the Aynak copper mine

  • Cash flow


This document is being processed or is not available.