Ratings for the Songo Songo Gas Development and Power Generation Project for Tanzania were as follows: outcomes were satisfactory; risk to development outcome was low or negligible; Bank performance was moderately satisfactory and borrower performance was also moderately satisfactory. Some lessons learned includes: the skill sets required for the power generation and gas components are different from the skill sets required to design and implement...
انظر المزيد
تفاصيل
-
2011/9/30
-
تقرير إنجاز تنفيذ ونتائج المشروع
-
ICR1819
-
1
-
1
-
2011/10/05
-
Disclosed
-
Tanzania - Songo Songo Gas Development and Power Generation Project
-
Environmental and Social Management Plan
تنزيل الملفات
تقرير كامل
نسخة رسمية من الوثيقة (قد تضم توقيعات، الخ)
-
Total Downloads** : 707