The objectives of the Electricity Expansion Project for Kenya are to: (a) increase access to electricity in urban, peri-urban and rural areas; and (b) improve the efficiency, reliability and quality of service to consumers, while sustaining the policy, institutional and regulatory environment needed for these results to materialize. Negative impacts include: soil erosion, contamination of soil, decreased air quality due to dust emission, solid waste...
انظر المزيد
الوثيقة أيضا متوفرة بـ
الإنجليزية,
الإنجليزية,
الإنجليزية,
الإنجليزية,
الإنجليزية,
الإنجليزية,
الإنجليزية,
الإنجليزية,
الإنجليزية
تفاصيل
-
2012/11/01
-
تقييم بيئي
-
SFG1101
-
4
-
2015/5/19
-
Disclosed
-
Environmental impact assessment project report for the proposed Chepseon 33/11 kV substation
-