Ratings for the Lom Pangar Hydropower Project for Cameroon were as follows: outcome and Bank performance was satisfactory and monitoring and evaluation (M and E) quality was substantial. Some lessons learned...
The development objective of Lom Pangar Hydroelectric Project for Cameroon is to increase hydropower generation capacity and reduce seasonal variability of water flow in the Sanaga River and to increase...
On December 1, 2017, the Inspection Panel received a Request for Inspection related to the Cameroon Lom Pangar Hydropower Project. The Request was submitted by two former workers of the Project who allege...